Prioritized Mitigation and Owner
Item Mitigation Strategy Owner
Too Many Clashes Include an early coordination Milestone, add coordination zones, and use Pull Planning in each Milestone to prioritize modeling tasks so that teams start modeling only when they can complete their work without interruption. BIM Manager